A LACK of daylight hours meant that yesterday’s turbine components delivery to Pines Burn Wind Farm concluded at the A6088 layby.

The journey will continue today Tuesday November 21.

READ MORE: Detectives probe break ins at homes in Galashiels and St Boswells

Set off time is planned for 9.30am.

The live tracker will be in operation.

READ MORE: Delays expected on A7 today due to scheduled abnormal load

Please note these timings are estimates. Please see the Facebook or twitter page for regular live updates.

The Pines Burn wind farm project is located approximately 6km Southwest of Bonchester Bridge and 8km South of Hawick in the Scottish Borders.

The project consists of 11 wind turbines, with tip heights between 130m, 145m and 149.9m.

The development will be operational for a 30-year period, after which the turbines would be removed, and the site restored.