THE latest wind turbine blade arrived safely onsite yesterday Monday December 11 at Pines Burn Wind Farm which is located approximately 6km Southwest of Bonchester Bridge and 8km South of Hawick.

The next scheduled movement date was today Tuesday December 12.

However that has now been cancelled due to adverse weather.

READ MORE: Farmfoods to open new store this week at former Halfords

The abnormal load convoy was set to leave its current location near St Boswells and travel via the A68, to the A699 to Selkirk. It will then travel south on the A7 to Hawick.

Set off time had been planned for the earlier time of 9am

READ MORE: Shanghai Banquet set to open for business in Tweedbank this week

The blade lifter can only move during daylight hours which means less time during the day to make the movements.

The next delivery is scheduled for Thursday December 14 at 9am.

Please note these timings are estimates.

A tracker will be deployed an available from when the convoy begins.

The tracker will be embedded into this article.